Header_logo-0605
Artist’s impression for illustrative purpose only

Development Schedule

Works for the development area covered by the RODP are planned to be implemented in two phases. Phase 1 mainly covers the I&T land parcels to the north of San Tin Highway/Fanling Highway, some residential land to the south and the key infrastructure areas with road connections. Phase 2 covers the remaining area. On present showing, site formation for I&T land will commence in Q4 2024 with formed sites coming on stream in 2026 the earliest. I&T enterprises may start operation earlier than 2031 subject to time required for building construction. The first population intake will start from 2031, while bulk population intake will start from 2034, around the time when the NOL Main Line commences operation.
©2024
Civil Engineering and Development Department and Planning Department
All Rights reserved